Riverside Development - Albert Town
Riverside Stage 5 was another quality development started in Nov
2004 that had all the engineering and surveying work completed by
Paterson Pitts Partners Ltd on behalf of the developer, Infinity Investment
Group.
The 52 lot development has sections ranging in size from 2000m²
to 4000m². Construction for the development commenced in May
2005 and was completed in October 2005. This work included extensive
engineering work with retaining walls and pavement construction due
to unstable ground. The majority of the existing native manuka &
kanuka vegetation was retained and extensive k-line watering has been
used to establish good grass coverage.